Design–bid–build (or design/bid/build, and abbreviated D–B–B or D/B/B accordingly), also known as Design–tender (or "design/tender") traditional method or hardbid, is a project delivery method in which the agency or owner contracts with separate entities for the design and construction of a project.
Design–bid–build is the traditional method for project delivery and differs in several substantial aspects from design–build.
There are three main sequential phases to the design–bid–build delivery method:
The design phase
The bidding (or tender) phase
The construction phase
In this phase the owner retains an architect (or consulting engineer for infrastructure works) to design and produce bid documents, including construction drawings and technical specifications, on which various general contractors will in turn bid to construct the project. For building projects, the architect will work with the owner to identify the owner's needs, develop a written program documenting those needs and then produce a conceptual and/or schematic design. This early design is then developed, and the architect will usually bring in other design professionals including a structural engineer, sometimes a civil engineer, mechanical, electrical, and plumbing engineers (MEP engineers), a fire protection engineer and often a landscape architect to help complete the construction drawings and technical specifications. The finished bid documents are coordinated by the architect and owner for issuance to general contractors during the bid phase.
Design fees are typically between 5-10% of the total project cost.
Construction bidding
Bidding can be "open", in which any qualified bidder may participate, or "select", in which a limited number of pre-selected contractors are invited to bid.
The various general contractors bidding on the project obtain copies of the bid (or tender) documents, and then put them out to multiple subcontractors for bids on sub-components of the project. Sub-components include items such as the concrete work, structural steel frame, electrical systems, HVAC, and landscaping.
This page is automatically generated and may contain information that is not correct, complete, up-to-date, or relevant to your search query. The same applies to every other page on this website. Please make sure to verify the information with EPFL's official sources.
Technologie du Bâti V aborde le bâtiment comme un système d'opérations techniques et culturelles invoquant des choix liés à l'environnement, au matériau, à la structure, et au montage. L'objectif du
Sensibiliser les étudiants à comprendre et concevoir des constructions en bois innovantes et intéressantes d'un point de vue architectural et structurel. Approfondir les connaissances techniques à tra
L'Unité introduira le dessin comme l'outil clé de la communication entre ingénieurs et architectes et comme médiateur entre la construction et l'étudiant. Grâce au dessin, nous analyserons des projets
Construction management (CM) is a professional service that uses specialized, project management techniques and software to oversee the planning, design, construction and closeout of a project. The purpose of construction management is to control the quality of a project's scope, time / delivery and cost—sometimes referred to as a project management triangle or "triple constraints." CM is compatible with all project delivery systems, including design-bid-build, design-build, CM At-Risk and Public Private Partnerships.
This page is a list of construction topics. Construction Abated Abrasive blasting AC power plugs and sockets Access mat Accrington brick Accropode Acid brick Acoustic plaster Active daylighting Adaptive reuse Aerial crane Aerosol paint Aggregate base Agile construction Akmon Alternative natural materials Anchorage in reinforced concrete Angle grinder Arc welding Artificial stone Asbestos cement Asbestos insulating board Asbestos shingle Asphalt concrete Asphalt roll roofing Autocla
Construction is a general term meaning the art and science to form objects, systems, or organizations, and comes from Latin constructio (from com- "together" and struere "to pile up") and Old French construction. To construct is the verb: the act of building, and the noun is construction: how something is built, the nature of its structure. In its most widely used context, construction covers the processes involved in delivering buildings, infrastructure, industrial facilities, and associated activities through to the end of their life.
The energy transition in Switzerland requires refurbishing 80% of the buildings stock, which will mobilize up to 70% of the construction workforce, leaving nearly no one to build new homes. How can we then accommodate 10.4 million people in 2050? ...
The destructive impact of the construction industry on the planet and its inhabitants is no longer in question. Global warming, waste management, depletion of natural resources, air and soil pollution are all issues that must be urgently addressed. They ar ...
The opening of the Guggenheim Museum in Bilbao in 1997 heralded the beginning of an era in world architecture defined by iconic buildings underpinned by mediatic exposure and the belief in the power of design to leverage urban conditions. Today, a conspic ...