In earthmoving, cut and fill is the process of constructing a railway, road or canal whereby the amount of material from cuts roughly matches the amount of fill needed to make nearby embankments to minimize the amount of construction labor.
Cut sections of roadway or rail are areas where the roadway has a lower elevation than the surrounding terrain. Fill sections are elevated sections of a roadway or trackbed. Cut and fill takes material from cut excavations and uses this to make fill sections. It costs resources to excavate material, relocate it, and to compact and otherwise prepare the filled sections. The technique aims to minimise the effort of relocating excavated material while also taking into account other constraints such as maintaining a specified grade over the route.
In addition to minimising construction cost, other factors influence the placement of cut or filled sections.
For example, air pollutants can concentrate in the valleys created by the cut section. Conversely, noise pollution is mitigated by cut sections since an effective blockage of line-of-sight sound propagation is created by the depressed roadway design.
The environmental effects of fill sections are typically favorable with respect to air pollution dispersal, but in respect to sound propagation, exposure of nearby residents is generally increased, since sound walls and other forms of sound path blockage are less effective in this geometry.
The reasons for creating fills include the reduction of grade along a route or the elevation of the route above water, swampy ground, or areas where snow drifts frequently collect. Fills can also be used to cover tree stumps, rocks, or unstable soil, in which case material with a higher bearing capacity is placed on top of the obstacle in order to carry the weight of the roadway or railway and reduce differential settlement.
The practice of cut-and-fill was widely utilized to construct tracks along rolling terrain across the British Isles.
This page is automatically generated and may contain information that is not correct, complete, up-to-date, or relevant to your search query. The same applies to every other page on this website. Please make sure to verify the information with EPFL's official sources.
In civil engineering, a cut or cutting is where soil or rock from a relative rise along a route is removed. The term is also used in river management to speed a waterway's flow by short-cutting a meander. Cuts are typically used in road, rail, and canal construction to reduce the length and grade of a route. Cut and fill construction uses the spoils from cuts to fill in defiles to cost-effectively create relatively straight routes at steady grades. Cuts are used as alternatives to indirect routes, embankments, or viaducts.
A road, railway line, or canal is normally raised onto an embankment made of compacted soil (typically clay or rock-based) to avoid a change in level required by the terrain, the alternatives being either to have an unacceptable change in level or detour to follow a contour. A cutting is used for the same purpose where the land is originally higher than required. Embankments are often constructed using material obtained from a cutting.
The grade (also called slope, incline, gradient, mainfall, pitch or rise) of a physical feature, landform or constructed line refers to the tangent of the angle of that surface to the horizontal. It is a special case of the slope, where zero indicates horizontality. A larger number indicates higher or steeper degree of "tilt". Often slope is calculated as a ratio of "rise" to "run", or as a fraction ("rise over run") in which run is the horizontal distance (not the distance along the slope) and rise is the vertical distance.
This study is within the frame of the construction of the rail link between Geneva Cornavin station, Eaux-Vives station and Annemasse (CEVA). The project area is located at a cut-and-cover tunnel built by slurry walls located in the alluvium of the Foron R ...
This study is within the frame of the construction of the rail link between Geneva Cornavin station, Eaux-Vives station and Annemasse (CEVA). The project area is located at a cut-and-cover tunnel built by slurry walls located in the alluvium of the Foron R ...
The rail link between Geneva Cornavin Station, Eaux-Vives Station and Annemasse (CEVA) is currently under construction including a cut-and-cover tunnel built by slurry walls located in the alluvium of the Foron River. The covered trench cuts the groundwate ...